SOLAR POWER STATION INSTALLATION (VILLAGE OF HORENKA)
- Capacity: 29.9 kW
- Module: JA Solar, 325 W
- Inverter: SolarEdge SE27.6k - 3phase 37.25
- Optimizers: SolarEdge P650-5R M4M RL (MC4)
- Mounting: Kripter - 1.6x1m
- Installation Period: 4 days
The goal of this project is to generate additional income by selling electricity at the 'green' tariff and to compensate for personal energy consumption. To connect the station, the power to the house was increased from 5 kW to 28 kW.
The station's payback period is 4 years, with an operational lifespan of 25 years. By the end of the 'green' tariff period, the station will generate income 2.5 times higher than the invested capital.
Every year, we conduct inspections of the power station, analyze module efficiency, check connections, and test the inverter in various load conditions.
Contact us: